Location: Level 3 E-Block, Frenchay Campus
Status: Works complete
Programme: 28th August 2012 until 20th November 2012
Project Cost: Circa £300k
Design Team: UWE Facilities (Estates)
Description of work: Full refurbishment of Level 3 E-Block. Works include asbestos removal, demolition of partition walls, upgrades to mechanical and electrical infrastructure, enhanced thermal performance of all rooms, new stud walls, flooring, ceiling, lighting, decorations and joinery.
BEFORE |
AFTER |
![]() |
![]() |
![]() |
![]() |
Further information: Please contact Phil Lawrence MRICS, 86510